action needed
The package has not entered testing even though the delay is over
normal
The package has not entered testing even though the 5-day delay is over.
Check why.
testing migrations
-
excuses:
- Migration status for chuck (1.5.2.5-1 to 1.5.4.1-1): BLOCKED: Maybe temporary, maybe blocked but Britney is missing information (check below)
- Issues preventing migration:
- ∙ ∙ missing build on ppc64el
- ∙ ∙ arch:ppc64el not built yet, autopkgtest delayed there
- Additional info:
- ∙ ∙ Piuparts tested OK - https://piuparts.debian.org/sid/source/c/chuck.html
- ∙ ∙ Reproducible on amd64 - info ♻
- ∙ ∙ Reproducible on arm64 - info ♻
- ∙ ∙ Reproducible on armhf - info ♻
- ∙ ∙ Reproducible on i386 - info ♻
- ∙ ∙ 16 days old (needed 5 days)
- Not considered